For the second instalment, works involved mainly, setting of scaffolds to enable work at high levels of the building at first and second floors, fabrication and installation of Aluminium windows and security metal grills for those levels, and for covering related contractual expenses. The works are as detailed below:

  1. Fabrication and fitting to the first floor 36 windows (Aluminium partitions, anodized powder coated bronze frames and 6 mm thick tinted glass) of different sizes. So far we have covered 90% of the work.
  2. Fabrication and installation of remained 13 security metal grills for windows and to the door tops at examinations storage room. So far we have covered 95% of the work.
  3. Fixing mortise locks, stoppers and related accessories which we have achieved 100%
  4. The activities as detailed in i and ii above, are scheduled for completion on 27thSeptember2019.