I lavori termineranno a fine aprile, ma la cosa importante è mantenere la comunicazione! Ecco un aggiornamento:

Dear Director,

Greetings from R.C. Diocese of Sivagangai, Tamil Nadu.

I am extremely sorry for the delay in reporting about the construction of two classrooms at Nedunthulasi where you are financing this project.

Since I was busy with other property related works, I could not do justice to this area. Hereafter I will be perfect in updating the report then and there. 

In fact, we are about to complete the work at Nedunthulasi and the work is in full swing now. We will finish by April 2020 and our Bishop is going to bless this building by next month

Kindly excuse me for the delay in the process.Thanking you for understanding.

Yours in Christ,

Fr. Stanislaus,

Project Secretary

Primo resoconto

La posa della prima pietra è stata fatta il 28 giugno 2019, Festa del Sacro Cuore di Gesù.

Stanno costruendo due classi, con le fondamenta già gettate e le colonne che si stagliano dalla base.

Purtroppo la mancanza di acqua ha causato ritardi nei lavori. Ora le cose vanno meglio.

Il progetto in sintesi

La R.C. Primary School è stata fondata 80 anni fa ed offre una scolarizzazione gratuita ai bambini poveri, poiché Nedunthulasi è un villaggio Dalit. Serve un comprensorio di 45 villaggi ed è situata a 13 Km dalla parrocchia di Irudayapuram . Vi lavorano insegnanti qualificati e motivati.

E’ stata costruita con fango e paglia e ormai è in condizioni instabili e precarie, con il tetto ormai collassato. Quindi attualmente gli studenti fanno lezione sotto gli alberi, perché stare all’interno non è più sicuro.

Si vuole quindi demolire il vecchio edificio, che è abbastanza grande perché all’inizio veniva utilizzato anche come chiesa, prima di essere utilizzato come scuola.

Si vogliono costruire due classi che possano ospitare 58 alunni.

Referente: Fr. T. Bhaskar David