The project has progressed very well, estimated to be at over 80% of phase 2 planned activities.
1. Structure for 1 st and 2nd floor
2. Walling for the 1st floor
3. Plastering and painting the 1st floor
4. Aluminum windows
5. Floor tiles for offices, washrooms (this activity is ongoing for classrooms)
6. Cabling for electrical and data completed by 60%
The speed with which the project activities are being carried out is greatly affected by the fact that ground floor is being used for school activities for up to 9 hours per day, leaving us only with 3 hours maximum for contractors to do their work.
I remain faithful to you
Fr Josephat Mmbaga, Ofmconv